Team Name: Online Health Monitoring System
Team Members:
CONTENTS:
Planned vs Actual Expenditures
Planned vs actual for each technical progress metric
For deliverables, we are on schedule. For coding, we are behind schedule. We had hoped to work on coding while working on Deliverables II. However, the detailed design was much more involved than anticipated. At this stage, we have some cushion for the code. Therefore, we are not too concerned with the code. No major issues encountered. No major changes are expected. There are no current issues.
Planned vs Actual Expenditures
The
detailed design was expected to take four hours per each module. However, it took a little longer than
expected.
Planned vs actual for each technical progress metric
It
is estimated that a little over 32% of the project is complete to date. We are on schedule for deliverables, but
behind schedule for coding.
See Appendix W8
The coding milestones were unrealistic. Realistically, we are not too far behind for code.