COP4331 Fall 2014 Online Health Monitoring System

 

Project Name: Online Health Monitoring System

Team Web site: link

Web Pages for Other Team Members:


Contents of this Document

Individual Weekly Time and Activity Log:

Week 15 (11/21/14 - 11/25/14)

Weekly statements of individual progress and status:

Project is finished.

 

Demo slides- 0.5 hours

Project Legacy- 2 hours (30% for total of 100%)

Deliverables III Revision and Compilation- 4.5 hours (100% for total of 100%)

Individual Lessons Learned- 0.5 hours (100% for total of 100%)

Admin- 6 hours

-log tally

-bi-weekly reports

-action items

-update website

 

Log of individual technical or management issues and their resolution:

None.

 

Defect log

None.

 

Notes, lessons learned, etc.

None.

Week 14 (11/14/14 - 11/20/14)

Weekly statements of individual progress and status:

Coding progress is caught up to schedule.

 

Team coding session- 4 hours

Code integration/debugging/testing/refactoring- 18.5 hours (40% for total of 100%)

Demo testing- 0.5 hours

Project Legacy- 1 hour (20% for total of 70%)

Pill/Appointment Manager Test Results- 2 hours (100% for total of 100%)

Pill/Appointment Manager User Manual- 1 hour (100% for total of 100%)

Summary of Work for Individual Lessons Learned- 2.5 hours (100% for total of 100%)

Individual Lessons Learned- 2 hours (100% for total of 100%)

Admin- 7 hours

-log tally

-bi-weekly reports

-action items

 

Log of individual technical or management issues and their resolution:

A few minor bugs caught by David.  These were quickly fixed.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Project Legacy- 3 hours (30% for total of 100%)

Admin- 3 hours

Compilation and Revision of Deliverables III- 4 hours (100% for total of 100%)

Week 13 (11/7/14 - 11/13/14)

Weekly statements of individual progress and status:

Coding progress is behind schedule.

 

Code Integration/Refactoring- 21 hours (90% for a total of 95%)

Administrative- 4 hours

-Configuration management

-Coding session agenda

-Project status assessment

 

Log of individual technical or management issues and their resolution:

Interface issues with database and navigator.  Plan to finish before coding session meeting.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Code Integration- 6 hours (95% for total of 100%)

Week 12 (10/31/14 - 11/6/14)

Weekly statements of individual progress and status:

Coding progress is behind schedule.

 

Code Research:  php, jQuery, AJAX, forms- 6.5 hours (100% for a total of 100%)

Code Integration- 6 hours (5% for a total of 5%)

Project Legacy- 3.5 hours (50% for a total of 50%)

Administrative- 2.5 hours

-Configuration management

-Major team website updates

-Project status assessment

 

Log of individual technical or management issues and their resolution:

Interfacing requires understanding php and a redo of my code.  Working hard this week to get the module working.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Code Integration- 10 hours (95% for total of 100%)

Week 11 (10/24/14 - 10/30/14)

Weekly statements of individual progress and status:

Progress is according to schedule.

 

Code- 12 hours (65% for a total of 70%)

Presentation- practice/print at Kinko’s- 1hour

 

Log of individual technical or management issues and their resolution:

Need to interface with database.  James is helping out.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Coding- 6 hours (30% for total of 100%)

Week 10 (10/17/14 - 10/23/14)

Weekly statements of individual progress and status:

Progress is according to schedule.

 

High-Level Design- 6 hours (50% for total of 100%)

Deliverables II:  Compile/Revise- 2 hours (75% for total of 100%)

Slide Presentation and Revision- 4.5 hours (100% for total of 100%)

Admin- 2 hours

-Meeting preparation and minutes

 

Log of individual technical or management issues and their resolution:

None.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Coding- 8 hours (95% for total of 100%)

Week 9 (10/10/14 - 10/16/14)

Weekly statements of individual progress and status:

Progress is according to schedule.

 

Pill/Appointment Manager slides- 1 hour (100% for total of 100%)

Deliverables II:  Compile Detailed Design- 1 hour (25% for total of 25%)

High-Level Design- 2 hours (25% for total of 50%)

Admin- 5.5 hours

-Meeting agenda and preparation

-Slide presentation outline and template

-Update website

 

Log of individual technical or management issues and their resolution:

None.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Slide Presentation- 2 hours (100% for total of 100%)

Project Management- 2 hours

High-Level Design- 4 hours (50% for total of 100%)

Deliverables II compilation- 3 hours (75% for total of 100%)

Week 8 (10/3/14 - 10/9/14)

Weekly statements of individual progress and status:

Progress is according to schedule.

 

Detailed Design- 9.5 hours (60% for total of 100%)

High-Level Design- 1 hour (25% for total of 25%)

Admin/Log Analysis/Bi-weekly Report- 3.5 hours

 

Log of individual technical or management issues and their resolution:

The deadline for Detailed Design is fast approaching.  Sent out a reminder this week.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Slides- 2 hours (100% for total of 100%)

Project Management- 3 hour

High-Level Design- 3 hours (75% for total of 100%)

Week 7 (9/26/14 - 10/2/14)

Weekly statements of individual progress and status:

Progress is according to schedule.

 

Detailed Design- 3.5 hours (40% for total of 40%)

Log Analysis/Bi-weekly Report- 2.5 hours

 

Log of individual technical or management issues and their resolution:

The deadline for Detailed Design is fast approaching.  Sent out a reminder this week.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Detailed Design- 4 hours (60% for total of 100%)

Project Management- 1 hour

Week 6 (9/19/14 - 9/25/14)

Weekly statements of individual progress and status:

Progress is according to schedule.

 

Deliverables II Meeting, Preparation and Minutes- 6 hours (100% for total of 100%)

Research HTML/JavaScript- 4 hours (100% for total of 100%)

Post revised Deliverables I documents on team website- 1 hour (100% for total of 100%)

 

Log of individual technical or management issues and their resolution:

None.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Detailed Design- 4 hours (75% for total of 75%)

Bi-weekly Project Report- 2 hours

Week 5 (9/12/14 - 9/18/14)

Weekly statements of individual progress and status:

Progress is according to schedule.

 

Deliverables I Revisions- 9 hours (100% for total of 100%)

Weekly Log Analysis/Bi-Weekly Report/Work Tally 7.5 hr

Individual webpage- post logs 1 hr

Deliverables II Meeting- 0.5 hr

 

Log of individual technical or management issues and their resolution:

Chris Chaffin and I sent email and communicated face-to-face this week.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

High-Level Design- 2 hours (33% for total of 33%)

Detailed Design- 2 hours (33% for total of 33%)

Research JavaScript- 3 hours (60% for total of 60%)

Week 4 (9/5/14 - 9/11/14)

Weekly statements of individual progress and status:

Progress is according to schedule.    

 

Project Management Plan- 8 hours (55% for total of 100%)

 

Log of individual technical or management issues and their resolution:

None.

 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Project Management Plan Revision- 1 hour (100% for total of 100%)

Revision of Deliverables I- 3 hours (100% for total of 100%)

Week 3 (8/29/14 - 9/4/14)

Weekly statements of individual progress and status:

Progress is according to schedule.  Minor issues are expected to be resolved by next week, allowing deadlines to be met.    

 

Project Management Plan- 6 hours (45% for total of 45%)

Research JavaScript- 0.25 hours (5% for total of 5%)

 

Log of individual technical or management issues and their resolution:

I encountered a little more complexity in the Project Management Plan than initially expected.  Project Management plan requires PERT chart and other diagrams.  These, in turn, require Visio or Microsoft Project.  Milestone chart and individual log template are precursors for other sections of the Project Management Plan.  These are relatively minor issues that will require more time next week.  Early next week, I plan to look into Visio and create the milestone chart and individual log template.  I also plan to study the class notes on PERT charts.  This should enable completion of the Project Management Plan.  No assistance will be required. 

Defect log

None.

 

Notes, lessons learned, etc.

Anticipated progress next week:

Project Management Plan- 6 hours (55% for total of 100%)