COP 4331 - Fall 2014 - Online Health Monitoring System 

  

Project Name:Online Health Monitoring System 

Team Web site: link 

Web Pages for Other Team Members: 

·         Jon Carelli - email - page 

·         Chris McCue - email - page 

·         Chris Chffin - email - page 

·         Ethan Pitts - email - page 

·         David Gundler - email - page 

·         James Luke - email - page 

  

Contents of this Document 

 

week 14 

Overall status this week: 

  Progress made. 

Progress this week: 

Code documentation and finish up work   12 hours (90% of 90%) 

Issues this week: 

 

 

 

week 13 

Overall status this week: 

  Progress made. 

Progress this week: 

code  6 hours (15% of 80%) 

Server and PHPMailer 4 hours(50% of 100%) 

Issues this week: 

Problems with the server and mailing and setting and starting my code. 

Will need help setting the server for mail if we go that way it is currently sending through a gamil account with some problems with the spam filter. If we are just run my code forever then just need the function to the database if we need to start and stop it will need to add to the docs system controls. 

 

 

week 12 

Overall status this week: 

 not much Progress made. 

Progress this week: 

code  6 hours (30% of 65%) 

Issues this week: 

No issues 

Anticipated progress next week: 

week 11 

Overall status this week: 

 not much Progress made. 

Progress this week: 

code  60 min (5% of 35%) 

side practice 30 min (100% of 100%) 

Issues this week: 

No issues 

Anticipated progress next week: 

  

  

  

week 10 

Overall status this week: 

 not much Progress made. 

Progress this week: 

code  3 hours (30% of 30%) 

Issues this week: 

No issues 

Anticipated progress next week: 

  

  

week 9 

Overall status this week: 

 not much Progress made. 

Progress this week: 

Power point started  45 min (100% of 100%) 

Issues this week: 

No issues 

Anticipated progress next week: 

  

week 8 

Overall status this week: 

 not much Progress made. 

Progress this week: 

Detailed Design started  4 hours  (90% of 100% total) 

Issues this week: 

No issues 

Anticipated progress next week: 

  

week 7 

Overall status this week: 

 not much Progress made. 

Progress this week: 

Detailed Design started  60 min (10% of 10% total) 

Issues this week: 

No issues 

Anticipated progress next week: 

  

week 6 

Overall status this week: 

 not much Progress made. 

Progress this week: 

some SMS research done if we use java 60 min (10% of 100%) 

team meeting 60 min(100% of 100%) 

Issues this week: 

time constraints 

Anticipated progress next week: 

  

9/19/2014 David Gundler Individual Log 

Overall status this week: 

 Progress made. 

Progress this week: 

Met with the TA with others members for the seconded required meeting 10min(50% for total 100%) 

Reviewed SRS SRS-1.0 hours(20% for total 100%) 

Issues this week: 

None. 

Anticipated progress next week: 

Research JavaScript 4hours(30% for total 38%) 

 

9/12/2014 David Gundler Individual Log 

Overall status this week: 

Progress made and the TA was met. The SRS seems all most done. 

Progress this week: 

Meet with the TA for the first required meeting 17min(50% for total 50%) 

Read what was done to SRS and added SRS-6.0 hours(75% for total 80%) 

Issues this week: 

Some issues with the SRS . SRS is all most filled out just need a TA to look over it. 

Anticipated progress next week: 

Finish SRS SRS-5.0 hours(20% for total 100%) 

 

  

9/05/2014 David Gundler Individual Log  

Overall status this week: 

 Progress made a little behind schedule.   

Progress this week: 

Research HTML-0.30 hours (5% for total of 5%) 

Research JavaScript-0.45 hours (8% for total of 8%) 

Research and Test possible SMS-3.0 hours(8% for total 10%) 

Read what was done to SRS and added SRS-1.0 hours(5% for total 5%) 

Personal page-0.25 hours(90% for total 90%)  

Issues this week: 

Some issues with  the SRS specifics. Will use class notes and book to clarify. Have all ready contacted TA to talk about specifics of the requirements of the project.  

Anticipated progress next week: 

Read what will be done to SRS and added SRS-9.0 hours(95% for total 100%) 

Research HTML-0.30 hours (5% for total of 10%) 

Research JavaScript-0.30 hours (7% for total of 15%) 

 

8/30/2014 David Gundler Individual Log  

Overall status this week: 

 Joined group. 

Progress this week: 

Research possible SMS-1.0 hours(2% for total 2%) 

Issues this week: 

Meeting up with group.Setting time to meet up. 

Anticipated progress next week: 

Research HTML-0.45 hours (5% for total of 5%) 

Research JavaScript-0.30 hours (5% for total of 5%) 

 

  