COP 4331 - Fall 2014 - Online Health Monitoring System
Project Name:Online Health Monitoring System
Team Web site: link
Web Pages for Other Team Members:
· David Gundler - email - page
Contents of this Document
11/13/2014 James Luke Individual Log
Overall status this week
Integrating the system
Progress this week
Chat integration - 5 hours (100% for total 100%)
Calendar functionality - 2 hours (100% for total 100%)
UI funvtion - 1 hour (100% for total 100%)
Issues this week
no issues
Anticipated progress next week
Finish Integration
11/6/2014 James Luke Individual Log
Overall status this week
Integrating the system
Progress this week
UI integration // AJAX - 4 hours (70% for total 100%)
Pill Manager functions // AJAX - 4 hours (100% for total 100%)
UI funvtion - 1 hour (100% for total 100%)
Issues this week
no issues
Anticipated progress next week
Finish Integration
10/30/2014 James Luke Individual Log
Overall status this week
Implemented sessions in the prototype
Progress this week
UI integration - 3 hours (30% for total 30%)
Issues this week
Working on getting php calls without loading a php page. Will probably need to do some sort of jQuery/AJAX calls. More complicated than I anticipated.
Anticipated progress next week
Integrate database/php work with the pill manager and chat manager.
10/24/2014 James Luke Individual Log
Overall status this week
Implemented sessions in the prototype
Progress this week
Prototype - 2 hours (20% for total 40%) -- moving on to "real" product next week anyway
Issues this week
No issues
Anticipated progress next week
Integrate database/php work with the interface module.
10/17/2014 James Luke Individual Log
Overall status this week
Working on prototype. Have a server set up with basic PHP/MySQL interaction.
Progress this week
Prototype - 4 hours (20% for total 20%)
Issues this week
No issues
Anticipated progress next week
Finish login/settings database work, start on sessions/cookies
10/10/2014 James Luke Individual Log
Overall status this week
Researching Databases/PHP
Progress this week
Detailed Design - 6 hours (100% for total 100%)
Issues this week
No issues
Anticipated progress next week
Work on the database, get familiar with PHP-MySQL interaction.
10/2/2014 James Luke Individual Log
Overall status this week
Researching Databases/PHP
Progress this week
Learning PHP/MySQL - 2 hours (25% for total 25%)
Issues this week
No issues
Anticipated progress next week
Prototype login implemented.
9/26/2014 James Luke Individual Log
Overall status this week
Configuring Web Server
Progress this week
Basic installs and configuration - 2 hours (100% for total of 100%)
Issues this week
No issues
Anticipated progress next week
Prototype login implemented.
9/19/2014 James Luke Individual Log
Overall status this week
(Not a whole lot)
Progress this week
Finish Test Plan - 2 hours (50% for total of 100%)
Issues this week
No issues
Anticipated progress next week
To be decided at meeting.