11/13/2014 James Luke Individual Log

Overall status this week

Integrating the system

Progress this week

Chat integration - 5 hours (100% for total 100%)

Calendar functionality - 2 hours (100% for total 100%)

UI funvtion - 1 hour (100% for total 100%)

Issues this week

no issues

Anticipated progress next week

Finish Integration


11/6/2014 James Luke Individual Log

Overall status this week

Integrating the system

Progress this week

UI integration // AJAX - 4 hours (70% for total 100%)

Pill Manager functions // AJAX - 4 hours (100% for total 100%)

UI funvtion - 1 hour (100% for total 100%)

Issues this week

no issues

Anticipated progress next week

Finish Integration


10/30/2014 James Luke Individual Log

Overall status this week

Implemented sessions in the prototype

Progress this week

UI integration - 3 hours (30% for total 30%)

Issues this week

Working on getting php calls without loading a php page. Will probably need to do some sort of jQuery/AJAX calls. More complicated than I anticipated.

Anticipated progress next week

Integrate database/php work with the pill manager and chat manager.


10/24/2014 James Luke Individual Log

Overall status this week

Implemented sessions in the prototype

Progress this week

Prototype - 2 hours (20% for total 40%) -- moving on to "real" product next week anyway

Issues this week

No issues

Anticipated progress next week

Integrate database/php work with the interface module.


10/17/2014 James Luke Individual Log

Overall status this week

Working on prototype. Have a server set up with basic PHP/MySQL interaction.

Progress this week

Prototype - 4 hours (20% for total 20%)

Issues this week

No issues

Anticipated progress next week

Finish login/settings database work, start on sessions/cookies


10/10/2014 James Luke Individual Log

Overall status this week

Researching Databases/PHP

Progress this week

Detailed Design - 6 hours (100% for total 100%)

Issues this week

No issues

Anticipated progress next week

Work on the database, get familiar with PHP-MySQL interaction.


10/2/2014 James Luke Individual Log

Overall status this week

Researching Databases/PHP

Progress this week

Learning PHP/MySQL - 2 hours (25% for total 25%)

Issues this week

No issues

Anticipated progress next week

Prototype login implemented.


9/26/2014 James Luke Individual Log

Overall status this week

Configuring Web Server

Progress this week

Basic installs and configuration - 2 hours (100% for total of 100%)

Issues this week

No issues

Anticipated progress next week

Prototype login implemented.


9/19/2014 James Luke Individual Log

Overall status this week

(Not a whole lot)

Progress this week

Finish Test Plan - 2 hours (50% for total of 100%)

Issues this week

No issues

Anticipated progress next week

To be decided at meeting.



Template created by G. Walton (GWalton@mail.ucf.edu) on August 15, 2000

This page last modified by James Luke on 9/19/2014