tasks Label Depends on Start Finish
Development Enviroment selection A   9/8/2014 9/18/2014
Deliverables 1 B   9/8/2014 9/18/2014
charcter creation C   9/18/2014 10/2/2014
Level creation D   9/18/2014 10/2/2014
Menu system E A,B 9/18/2014 10/2/2014
Character customization F C,E 10/2/2014 10/15/2014
charcter leveling G F 10/2/2014 10/15/2014
NPC Merchant  H F 10/2/2014 10/20/2014
Enemy Creation I F 10/2/2014 10/20/2014
In level items J D 10/5/2014 10/20/2014
Inventory system K   10/15/2014 10/27/2014
Game Play (component testing) L E 10/27/2014 11/1/2014
Enemy Interaction M D 10/27/2014 11/18/2014
Interupt handleing N   11/1/2014 11/18/2014
Game play (Acceptance testing) O   11/18/2014 11/24/2014